The Supreme Court held that a home‑buyer’s right to a refund with interest for delayed possession is "absolute and unconditional"
The apex court confirmed that builders must honour contractual timelines and that any compensation for delay cannot be stacked with other reliefs .
Karnataka RERA ordered a refund of ₹31.46 lakh plus interest because the developer failed to hand over the plot as promised .